Additional information available at www.iloveapopka.net
Motorola Timeline - City of Apopka Mesh Project Plan - January 2010
- Installation of Planned Devices/Sites (Complete) October 2009
- Network Optimization (Complete) November 2009
- Performance Audit (Complete) December 2009
- Current Status
482 devices / sites installed 450 connected remainaing 32 sites awaiting power, fill-in IAP backhaul or relocation Alarms counts average in the signal digits and approximately 1-2% of network
- Remaining Deployment (in progress) January 2010 **
Errol Estates (deploying!) Design completed, 37 devices/sites and equipment is awaiting installation 12 devices installed, 6 connected to WMS, 25 to go awaiting PE pole swaps
- Wekiva Glen (pending)
Preliminary designed completed (12 devices/sites) Awaiting HOA approval from 1/14 HOA Board Review
- Performance Audit Report Presentation (Jan 21st)
Evaluation of Fill-in devices / sites (in progress) Site Survey of Potential Sites (in progress) Selection & Schedule of Remaining Fill-In Site Deployment (in progress)
- Punchlist items (in progress)
IAP Pole Surge/Grounding Upgrades (in progress) Canopy CMM/AP Surge/Grounding (currently being scheduled) City Technical Staff Training for MotoMESH and WMS (Jan 25th & 26th)
- Transition into Service (in progress, rolling migration)
Phase 1 – PTP and Canopy CMM / AP equipment under monitor and service mode.
- Remaining Deployment (in progress) February 2010 **
Errol Estates (completing) Wekiva Glen (TBD based on HOA approval) Punchlist items (in progress) IAP Pole Surge/Grounding Upgrades (completing) Canopy CMM/AP Surge/Grounding (completing) Design/Implementation of Remaining Fill-In Sites from Performance Audit (in progress) Transition into Service (in progress, rolling migration) Phase 2 – Canopy SM & Prizism application under monitor and service mode Local Device Reset
- Remaining Deployment (in progress) March 2010 **
Wekiva Glen (TBD based on HOA approval)
- Punchlist items (completing)
Remaining Implementation of Fill-In Sites from Performance Audit (completing) (dependant on supply of power from PE)
- Transition into Service (completing)
Phase 3 – MotoMESH Devices and WMS under monitor and service mode.
- 2 Year Warranty
** Completion subject to and dependent upon power supplied and pole swaps completed by Progress Energy |